Krusinski Construction completed a multi-phase project at CN Railway’s facility in Homewood, Illinois, including extensive roof replacements and a second-floor interior renovation.

Roofing work was completed in phases from 2016 to 2018, involving full demolition of existing systems and installation of a fully adhered 60-mil EPDM roofing system. The phased replacements covered approximately 115,000 SF in 2016, 94,000 SF in 2017, and the remaining areas in 2018.

In 2017, Krusinski renovated 6,000 SF of mechanical office space on the second floor. The work included new flooring, ceilings, LED lighting, plumbing fixtures, millwork, and full furniture replacement. The updated layout also introduced additional cubicle space, a breakroom, and a large conference room. All work was completed without disruption to CN’s ongoing operations.

Square
Footage
110,000
Market
Sector
Corporate Office | Interiors
Architect
Garnett Architects